Funding Information
(USD)
Total Actual Commitments:
9,009,215
USD
Total Planned Commitments:
0
USD
Total Actual Disbursements:
5,252,823
USD
Total Planned Disbursements:
7,099,343.67
USD
Organisation information
Activity created by:
UNDP
User
Activity created on:
26/10/2011
Activity updated on:
31/07/2019
Created in workspace:
United Nations Development Programme (UNDP) -
Team
Workspace manager:
UNDP
User -
undp@amp.org
Computation:
Yes
Identification
Project title:
Strengthening Institutional Capacity of the National Parliament in Timor-Leste - FED/2011/267807
ATP ID:
87292381484
Status:
Ongoing
Expected Outcomes:
Enhanced institutional capacity, knowledge of MPs and expertise of staff, which in turn will enhance the Parliament's ability to fulfill its mandate in overseeing the Executive
Description:
The overall objective is to enhance institutional capacity, knowledge of Members of Parliament and expertise of staff, which in turn will improve the Parliament’s ability to fulfil its mandate in overseeing the Executive.
Final Project Results:
Planning processes of the Parliament Administration improved. Secretariat's administrative procedures updated. Procurement and asset management system improved. Capacities of MPs to draft, scrutinize, amend and approve laws enhanced as a result of on-the-job trainings to MPs and capacity development training programmes to national legal drafters. Budgeting processes enhanced as a result of capacity development training programmes for both Secretariat staff and MPs. Pilote transcription system developed and implemented and capacity development training programmes initiated. MPs knowledge on anti-corruption issues enhanced.
Funding Organizations and Internal Project IDs:
Organization Name: United Nations Development Programme
Organization Acronym: UNDP
Organization Group: United Nations
Organization Type: Multilateral
Organization Code: UNDP
Agency Internal IDs
[United Nations Development Programme]
FED/2011/267-807
Activity Schedule
Date of Signed Agreement :
21/07/2011
Proposed Start Date:
01/08/2011
Actual Start Date:
01/08/2011
Proposed Completion Date:
28/02/2015
Actual Completion Date:
Final Date for Contracting:
Location
[Timor-Leste]
[Dili]
[Vera Cruz]
100%
Implementation Level:
Municipality Level
Implementation Location:
Municipality
National Plan
[Strategic Development Plan Pillars] [SOCIAL CAPITAL] [EDUCATION AND TRAINING]
50.0%
[Strategic Development Plan Pillars] [INSTITUTIONAL FRAMEWORK] [PUBLIC SECTOR MANAGEMENT AND GOOD GOVERNANCE ]
50.0%
SDP
Sectors
Primary Sector
DAC-CRS Sector Scheme
-
150 - GOVERNMENT AND CIVIL SOCIETY
(100)%
Development Partner Funding
ACTUAL DISBURSEMENT:
Actual
31/12/2012
12,481 USD
SUBTOTAL ACTUAL DISBURSEMENT:
12,481 USD
Undisbursed Balance:
-12,481 USD
ACTUAL DISBURSEMENT:
Actual
31/12/2011
12,513 USD
Actual
30/06/2012
77,893 USD
Actual
30/09/2012
-29,095 USD
Actual
31/12/2012
38,393 USD
Actual
31/03/2013
36,393 USD
Actual
30/06/2013
160,079 USD
Actual
30/09/2013
-80,276 USD
Actual
31/12/2013
1,283,096 USD
Actual
31/03/2014
54,927 USD
Actual
30/06/2014
91,847 USD
Actual
30/09/2014
23,471 USD
Actual
31/12/2014
1,701,141 USD
Actual
31/03/2015
192,335 USD
Actual
30/06/2015
249,267 USD
Actual
30/09/2015
20,136 USD
Actual
31/12/2015
439 USD
SUBTOTAL ACTUAL DISBURSEMENT:
3,832,559 USD
Undisbursed Balance:
-3,832,559 USD
ACTUAL DISBURSEMENT:
Actual
31/12/2011
55,947 USD
Actual
30/06/2012
132,752 USD
Actual
30/09/2012
248,312 USD
Actual
31/12/2012
253,414 USD
Actual
31/03/2013
217,012 USD
Actual
30/06/2013
333,381 USD
Actual
30/09/2013
441,507 USD
Actual
31/12/2013
-719,658 USD
Actual
31/03/2014
479,291 USD
Actual
30/06/2014
475,331 USD
Actual
30/09/2014
497,207 USD
Actual
31/12/2014
-1,070,919 USD
Actual
31/03/2015
26,217 USD
Actual
30/06/2015
25,018 USD
Actual
30/09/2015
12,971 USD
SUBTOTAL ACTUAL DISBURSEMENT:
1,407,783 USD
Undisbursed Balance:
-1,407,783 USD
Actual Commitments
Actual
01/01/2011
5,500,000 USD
Actual
31/12/2014
2,786,430 USD
Actual
31/12/2015
722,785 USD
Subtotal Actual Commitments:
9,009,215 USD
PLANNED DISBURSEMENT
Planned/Under Preparation
01/01/2011
413,252.67 USD
Planned Percentage for Minor and Capital Development: 30.0 %
Planned/Under Preparation
01/01/2012
1,358,074 USD
Planned Percentage for Minor and Capital Development: 30.0 %
Planned/Under Preparation
31/12/2013
1,702,910 USD
Planned Percentage for Minor and Capital Development: 30.0 %
Planned/Under Preparation
31/12/2014
2,902,322 USD
Planned/Under Preparation
31/12/2015
722,785 USD
Subtotal Planned Disbursement:
7,099,343.67 USD
Undisbursed Balance:
9,009,215 USD
Total Actual Commitments:
9,009,215 USD
Total Planned Disbursements:
7,099,343.67 USD
Total Actual Disbursements:
5,252,823 USD
Undisbursed Balance:
3,756,392 USD
Delivery rate:
58%
Related Documents
Related Organizations
Donor Organization
Executing Agency
United Nations Development Programme
100 %
Implementing Agency
United Nations Development Programme
100 %
RDTL Beneficiary Institutions
National Parliament
100 %
RDTL Beneficiary Institution Divisions
National Parliament - Parliamentary Secretariat
100 %
Contact Information
Global Partnership Indicators
Indicator 1
Does this project use the country results framework?
Indicator 6
Is this project on budget and subject to parliamentary scrutiny?
Indicator 9b
Does the project use national budget execution procedures?
Does the project use national financial reporting procedures?
Does the project use national auditing procedures?
Does the project use national procurement systems?
Support to Government Sector
Has this project been formally agreed upon (i.e. memorandum of understanding, project agreement, etc.) with a Government entity?
Activity Sites
Dili
Title
Dili
Description
15110.03 Institutional capacity building, Government Strengthening Institutional Capacity of the National Parliament in Timor-Leste.
" - EDUCATION AND TRAINING
- PUBLIC SECTOR MANAGEMENT AND GOOD GOVERNANCE"
Latitude
-8.55861
Longitude
125.57361
Dili
Title
Dili
Description
capital of a political entity
Latitude
-8.5586
Longitude
125.5736