Funding Information
(USD)
Total Actual Commitments:
1,938,861
USD
Total Planned Commitments:
0
USD
Total Actual Disbursements:
1,688,594
USD
Total Planned Disbursements:
660,911
USD
Organisation information
Activity created by:
IOM
User
Activity created on:
04/05/2016
Activity updated on:
20/04/2019
Created in workspace:
International Organization for Migration (IOM) -
Team
Workspace manager:
IOM
User -
iom@amp.org
Computation:
Yes
Identification
Project title:
DISASTER RISK REDUCTION – BUILDING COMMUNITY RESILIENCE IN TIMOR-LESTE (DRRBCR) PHASE III
ATP ID:
87292819914
Status:
Completed
Expected Outcomes:
1. The capacity to manage DRM and DRR programs at the national and municipality levels is strengthened.
2. Vulnerable communities in Timor-Leste acquire knowledge and skills to cope with hazard-related shocks and improve disaster preparedness.
3. Increased public awareness of disaster risk, vulnerability and mitigation actions, including options to mitigate negative effects of the El Nino.
4. Maintain emergency rapid response capacity in support of the GoTL contingency plans which will enable the provision of timely humanitarian assistance in the event of localized disasters.
Description:
The project aims to contribute to strengthening disaster risk reduction and preparedness measures and enhance resilience at the national, municipality and community levels across Timor-Leste. This will be achieved through four primary outcome areas: strengthening national capacity, promoting community resilience, expanding public awareness, and enhancing emergency response capability.
Final Project Results:
Allocations for Gender Equality
Indirect Allocation
Funding Organizations and Internal Project IDs:
Organization Name: Office of Foreign Disaster Assistance
Organization Acronym: US OFDA
Organization Group: United States
Organization Type: Bilateral
Organization Code: US OFDA
Agency Internal IDs
[Office of Foreign Disaster Assistance]
Activity Schedule
Date of Signed Agreement :
Proposed Start Date:
01/01/2017
Actual Start Date:
01/01/2017
Proposed Completion Date:
30/09/2018
Actual Completion Date:
30/09/2018
Final Date for Contracting:
30/09/2018
Location
Implementation Level:
National
Implementation Location:
Country
National Plan
[Strategic Development Plan Pillars] [SOCIAL CAPITAL] [EDUCATION AND TRAINING]
100.0%
SDP
Sectors
Primary Sector
DAC-CRS Sector Scheme
-
700 - HUMANITARIAN AID
-
-- 740 - Disaster prevention and preparedness
(100)%
Development Partner Funding
ACTUAL DISBURSEMENT:
Actual
30/04/2016
4,885.79 USD
Actual
31/05/2016
6,304.85 USD
Actual
30/06/2016
5,154.23 USD
Actual
31/07/2016
9,672.39 USD
Actual
31/08/2016
20,269.37 USD
Actual
30/09/2016
16,722.71 USD
Actual
31/10/2016
16,162.67 USD
Actual
30/11/2016
12,331.33 USD
Actual
31/12/2016
18,258.45 USD
Actual
31/01/2017
11,676.79 USD
Actual
28/02/2017
17,937.4 USD
Actual
31/03/2017
13,480.41 USD
Actual
30/04/2017
40,189.53 USD
Actual
31/05/2017
29,316.34 USD
Actual
30/06/2017
25,860.88 USD
Actual
31/12/2017
206,166.7 USD
Actual
31/03/2018
50,932.72 USD
Actual
30/06/2018
53,416.38 USD
Actual
30/09/2018
106,821.21 USD
Actual
31/12/2018
16,109.54 USD
SUBTOTAL ACTUAL DISBURSEMENT:
681,669.69 USD
Undisbursed Balance:
-681,669.69 USD
PLANNED DISBURSEMENT
Planned/Under Preparation
31/12/2018
660,911 USD
Subtotal Planned Disbursement:
660,911 USD
ACTUAL DISBURSEMENT:
Actual
30/04/2016
16,461.84 USD
Actual
31/05/2016
31,692.21 USD
Actual
30/06/2016
33,869.67 USD
Actual
31/07/2016
44,661.57 USD
Actual
31/08/2016
45,757.49 USD
Actual
30/09/2016
45,161.61 USD
Actual
31/10/2016
48,757.36 USD
Actual
30/11/2016
45,975.22 USD
Actual
31/12/2016
29,178.91 USD
Actual
31/01/2017
29,324.04 USD
Actual
28/02/2017
31,683.25 USD
Actual
31/03/2017
47,607.71 USD
Actual
30/04/2017
42,530.39 USD
Actual
31/05/2017
44,028.09 USD
Actual
30/06/2017
44,813.4 USD
Actual
31/12/2017
241,787.12 USD
Actual
30/06/2018
54,831.42 USD
Actual
30/09/2018
98,315.73 USD
Actual
31/12/2018
393.12 USD
SUBTOTAL ACTUAL DISBURSEMENT:
976,830.15 USD
Undisbursed Balance:
-976,830.15 USD
Actual Commitments
Actual
01/01/2017
1,938,861 USD
Subtotal Actual Commitments:
1,938,861 USD
ACTUAL DISBURSEMENT:
Actual
31/12/2017
270 USD
Actual
31/03/2018
337.5 USD
Actual
30/06/2018
2,433.16 USD
Actual
30/09/2018
27,053.5 USD
SUBTOTAL ACTUAL DISBURSEMENT:
30,094.16 USD
Undisbursed Balance:
1,908,766.84 USD
Total Actual Commitments:
1,938,861 USD
Total Planned Disbursements:
660,911 USD
Total Actual Disbursements:
1,688,594 USD
Undisbursed Balance:
250,267 USD
Delivery rate:
87%
Related Documents
Related Organizations
Donor Organization
Office of Foreign Disaster Assistance
Implementing Agency
International Organization for Migration
34 %
Association of Community Radios in Timor-Leste
33 %
RDTL Beneficiary Institutions
Ministry of Social Solidarity and Inclusion
100 %
RDTL Beneficiary Institution Divisions
Ministry of Social Solidarity - National Directorate of Disaster Management
100 %
Contact Information
Global Partnership Indicators
Indicator 1
Does this project use the country results framework?
No
Indicator 6
Is this project on budget and subject to parliamentary scrutiny?
No
Indicator 9b
Does the project use national budget execution procedures?
No
Does the project use national financial reporting procedures?
No
Does the project use national auditing procedures?
No
Does the project use national procurement systems?
No
Support to Government Sector
Has this project been formally agreed upon (i.e. memorandum of understanding, project agreement, etc.) with a Government entity?
No
Activity Sites