Projetu: Títulu:
PPTA 8750-TIM: Urban Services Improvement Sector Project
ATP nia ID: 872923611999
Estatutu:
Kompleta ona
Rezultadus (outcomes)ne'ebé hakarak atu atinje:
The outcome of the TA to have a Dili urban water supply master plan.
Deskrisaun:
The project preparatory TA will: (i) conduct assessments of existing water supply and solid waste management systems, including surveys and stakeholder consultations; (ii) develop water supply and solid waste investment strategies for Dili to help identify and prioritize project components for the ensuing loan project; (iii) determine the feasibility of the proposed investments for priority infrastructure and systems improvements, (iv) ensure that detailed design work supervised by DNSA is carried out to the required quality, and (v) identify appropriate project management arrangements to ensure that MOP and Estatal have adequate capacity to implement the project.
Rezultadus Ikus Projetu nian:
(i) Dili urban water supply master plan; (ii) Dili water supply public-private partnership feasibility study; (iii) Timor-Leste water sector tariff study; (iv) Dili sanitation and drainage master plan; (v) Second district capitals water and sanitation masterplans.
Alokasoins ba Egualidade Jéneru
Laiha Atribuisaun
ID Organizasaun Finansiamentu no Projetu Internál sira nian:
- Organization Name: Asian Development Bank
- Organization Acronym: ADB
- Organization Group: Asian Development Bank Group
- Organization Type: Multilateral
- Organization Code: ADB
|
Data Akordu Asinadu:
02/12/2014
Dataatu Hahú ne'ebé propoin:
02/12/2014
Data Hahú Aktuál :
02/12/2014
Data atu Remata ne'ebé propoin:
30/06/2016
Data Kompletu Aktuál:
30/06/2018
Data Ikus ba Kontratasaun:
|
Nivel implementasaun:
|
Nasionál
|
|
Fatin Implementasaun:
|
Nasaun
|
|
[Strategic Development Plan Pillars] [INFRASTRUCTURE DEVELOPMENT] [WATER AND SANITATION]
|
100.0% |
Primary Sector
|
DAC-CRS Sector Scheme
-
140 - WATER SUPPLY AND SANITATION
|
(100)%
|
|
|
|
|
Komitementus Aktuál
|
|
|
Aktuál
|
02/12/2014
|
1,480,000 USD
|
| Kompromisu Atual subtotal:
|
1,480,000 USD
|
|
|
|
PAGAMENTU NE'EBÉ PLANEIA ONA
|
|
|
Planeia ona/Prepara daudaun
|
30/06/2018
|
1,480,000 USD
|
|
Sub-Totál Pagamentu sira ne'ebé planeia ona :
|
1,480,000 USD
|
|
|
|
DEZENBOLSU AKTUÁL:
|
|
|
Aktuál
|
30/06/2015
|
204,610 USD
|
|
Aktuál
|
31/12/2015
|
618,171 USD
|
|
Aktuál
|
30/06/2016
|
USD
|
|
Aktuál
|
30/12/2016
|
104,147 USD
|
|
Aktuál
|
30/06/2017
|
297,080 USD
|
|
Aktuál
|
30/06/2018
|
45,525 USD
|
|
SUB-TOTÁL PAGAMENTU EFETIVU:
|
1,269,533 USD
|
|
|
|
Saldu ne'ebé la'ós pagu:
|
210,467 USD
|
|
|
|
|
|
| |
|
Totál Kompromisu Efetivu sira: |
1,480,000 USD
|
|
|
Totál Pagamentu sira ne'ebé planeia ona: |
1,480,000 USD
|
|
|
Totál Pagamentu Efetivu sira: |
1,269,533 USD
|
|
|
Saldu ne'ebé la'ós pagu: |
210,467 USD
|
|
|
Taxa entrega:
|
86%
|
|
|
|
Organizasaun Doadór
Ajénsia Ezekusaun
-
Asian Development Bank
100 %
|
Ajénsia Implementasaun
-
Ministry of Public Works
100 %
|
RDTL Instituisaun Benefisiariu
-
Ministry of Public Works
100 %
|
Divizaun Instituisaun Benefisiariu RDTL
-
Ministry of Public Works, Transport and Communication - National Directorate of Water, Sanitation and Urbanisation
100 %
|
|
Indikadór 1
|
|
Karik projetu ida ne'e uza nasaun nia kuadru-serbisu ba rezultadus?
|
|
|
Indikadór 6
|
|
Projetu ne'e hala'o tuir orsamentu no iha eskrutíniu parlamentár?
|
|
|
Indikadór 9b
|
|
Karik projetu ne'e uza prosedimentus nasionál ba ezekusaun orsamentál?
|
|
|
Karik projetu ne'e uza prosedimentus nasionál ba relatóriu finanseiru?
|
|
|
Karik projetu ne'e uza prosedimentus nasionál ba auditória?
|
|
|
Karik projetu ne'e uza sistemas nasionál ba aprovizionamentu?
|
|
|
Apoiu ba Setór Governu
|
|
Karik projetu ne'e formalmente konkordadu tiha ona (mak hanesan: iha memorandu de entendimentu, akordu projetu, nsst.) ho entidade Guvernu nian ida?
|
|
|