Funding Information  (USD)
Total Actual Commitments:
88,255.23 USD
Total Planned Commitments:
0 USD
Total Actual Disbursements:
88,255.23 USD
Total Planned Disbursements:
0 USD
Organisation information
Activity created by:
JICA User
Activity created on:
12/01/2018

Activity updated on:
08/02/2019
Created in workspace:
Japan - Team
Workspace manager:
JICA User - jica@amp.org
Computation:
Yes
 
Identification
Project title: 
Construction of Water Supply System in Hae-Coni and Osso Huna Villages, Baguia Administrative Post, Baucau Municipality
ATP ID: 
872924012589

Status:  Completed
Expected Outcomes: 

For the improvement of access to clean water, a water supply system will be constructed including filter tank, hydro motor pump, reservoir tanks, distribution tanks, public taps and water pipes. In addition to the material support, a training program will be provided to water committee members on ways to use and managign the water supply system.


Description: 

Construction a water supply system in Hae-Coni and Osouna Villlages, Baguia Administrative Post, Baucau Municipality.


Final Project Results: 



Funding Organizations and Internal Project IDs: 
Agency Internal IDs
Activity Schedule

Date of Signed Agreement :  21/11/2017
Proposed Start Date: 
Actual Start Date:  27/11/2017
Proposed Completion Date:  31/10/2018
Actual Completion Date:  30/11/2018
Final Date for Contracting: 
Location
[Timor-Leste] [Baucau] 100%

Implementation Level: Municipality Level

Implementation Location: Municipality

National Plan
[Strategic Development Plan Pillars] [ECONOMIC DEVELOPMENT] [RURAL DEVELOPMENT] 100.0%

SDP
Sectors
Primary Sector
DAC-CRS Sector Scheme - 140 - WATER SUPPLY AND SANITATION (100)%

Development Partner Funding
Organization Name : Government Of Japan
Organization Role : donor
Type Of Assistance : Grant
Aid Modality : Project Support
Actual Commitments
Actual 30/11/2017 88,255.23 USD  
Subtotal Actual Commitments: 88,255.23 USD    
ACTUAL DISBURSEMENT:
Actual 30/11/2017 88,255.23 USD  
  Recipient: Alfa Star as the Implementing Agency 
SUBTOTAL ACTUAL DISBURSEMENT: 88,255.23 USD    
Undisbursed Balance: 0 USD    


 
Total Actual Commitments: 88,255.23 USD    
Total Actual Disbursements: 88,255.23 USD    
Undisbursed Balance: 0 USD    
Delivery rate: 100%   
Related Documents
Related Organizations
Donor Organization
  • Government Of Japan

Executing Agency
  • Government Of Japan 100 %

Implementing Agency
  • Alfa Star 100 %

RDTL Beneficiary Institutions
  • Ministry of Public Works, Transport and Communication 100 %

Contact Information
Global Partnership Indicators
Indicator 1
Does this project use the country results framework?

  • Indicator 6
    Is this project on budget and subject to parliamentary scrutiny?

  • Indicator 9b
    Does the project use national budget execution procedures?

  • Does the project use national financial reporting procedures?

  • Does the project use national auditing procedures?

  • Does the project use national procurement systems?

  • Support to Government Sector
    Has this project been formally agreed upon (i.e. memorandum of understanding, project agreement, etc.) with a Government entity?
  • Yes

  • Activity Sites